We provide project updates on our blog for community members, donors, and partners to learn about how the project is progressing. These updates will be a result of meeting outcomes surrounding building planning, fundraising, communications and programming initiatives for the new facility.  Project details and economic impact details can always be found here: https://elkhartcenter.com/ and click here to make inquiries about the project.

APRIL 2019

BUILDING

  • Continued to tie-in MEP overhead rough-ins in all areas

  • Poured competition pool deck and began gutter tile

  • Finished remaining walls in fitness pool areas

  • Commenced aluminum door frame installation

  • Continued installation of Z Girts, flashing, and metal panels around the building

  • Completed roof membrane in all areas

  • Continued to install window frames and glazing around building

  • Installed lighting in all areas with finished ceilings

  • Continued painting in all areas except unit H

  • Installed grid ceiling in Units A, D and E

  • Received racquetball courts and began installation

  • Received gymnasium flooring

  • Installed grand stair

  • Began casework installation

  • Began toilet and shower partition installation

  • Energized permanent electric switchgear

  • Began mechanical equipment start up

  • Started site improvements on the building’s North and East sides

  • Started EIFS on south elevation