We provide project updates on our blog for community members, donors, and partners to learn about how the project is progressing. These updates will be a result of meeting outcomes surrounding building planning, fundraising, communications and programming initiatives for the new facility.  Project details and economic impact details can always be found here: https://elkhartcenter.com/ and click here to make inquiries about the project.

MAY 2019

BUILDING

  • Completed majority of tile mud set in Unit C pool

  • Completed all ceramic tile on fitness pool deck

  • Completed final painting of all remaining walls in fitness/therapy pools

  • Continued aluminum door frame installation, interior and exterior

  • Continued installation of metal siding panels around the building

  • Continued to install window frames and glazing on interior and exterior of building

  • Installed lighting and devices in all areas with finished ceilings

  • Started finish painting in all areas completed

  • Continued installing ceiling grid and tile in all areas

  • Continued finishing drywall in Units F, G, & H

  • Followed drywall finishing with painting and trim thru out building

  • Completed installation of racquetball courts

  • Installed gymnasium flooring, sanded, and sealed wood ready fro striping

  • Continued casework installation thru out building

  • Completed toilet and shower partition installation

  • Continued trimming out and setting fixtures in all locker rooms and Unit E

  • Continued site improvements on the building’s north and east sides

  • Completed EIFS on south elevation at Unit G

  • Started elevator installation

  • Completed exterior CMU screen wall and column enclosures in Unit C

  • Completed LVT and carpet installation in Unit E