We provide project updates on our blog for community members, donors, and partners to learn about how the project is progressing. These updates will be a result of meeting outcomes surrounding building planning, fundraising, communications and programming initiatives for the new facility.  Project details and economic impact details can always be found here: https://elkhartcenter.com/ and click here to make inquiries about the project.

MARCH 2019

BUILDING

  • Continued to tie-in MEP overhead rough-ins in all areas

  • Poured pool deck of fitness and therapy pools and

  • Backfilled competition pool walls

  • Completed installation of gutter on perimeter of competition pool

  • Completed hanging drywall, mud, and taped drywall in Units A, D, E, F, G & H on both floors

  • Continued installation of Z Girts, flashing, and metal panels around the building

  • Continued to install window frames and glazing around building

  • Installed lighting in Unit E fitness area, office area, Unit D locker rooms, and under track

  • Roughed in overhead lighting conduit for Units G & H

  • Completed painting of exposed steel under track

  • Continued to paint primer and 1st coat of finish on Unit E office area, and Units A & D 2nd floor

  • Completed installation of tile sand bed on Unit A pool deck and started tile installation

  • Completed framing and hanging drywall on soffits around the track, observation deck, and in front of racquetball courts

  • Installed Unit D135 stair, Unit F emergency stair, and handrail on straights of track

  • Completed setting all roof top equipment