We provide project updates on our blog for community members, donors, and partners to learn about how the project is progressing. These updates will be a result of meeting outcomes surrounding building planning, fundraising, communications and programming initiatives for the new facility.  Project details and economic impact details can always be found here: https://elkhartcenter.com/ and click here to make inquiries about the project.

JANUARY 2019

BUILDING

  • Continued to rough-in MEP in walls of Units D and H

  • Poured remaining floor slab on deck in Unit F and G track level

  • Finished excavating, forming, installed rebar, and poured shallow end of competition pool

  • Continued to trim out Unit A fitness and therapy pools

  • Laid CMU exterior wall of Unit B and 95% of all CMU walls inside Unit B

  • Continued to frame interior metal stud bulkheads in Units E, F, G, and H

  • Started hanging dry wall in Unit E and topped out walls in Unit H

  • Continued to install window frames and glazing around building

  • Continued to spray foam insulation around building

  • Started painting overhead decks in Unit E, F, and G

  • Started ceramic tile in restrooms

  • Installed roof membrane on Unit G stair tower and F & G radius entry canopies