We provide project updates on our blog for community members, donors, and partners to learn about how the project is progressing. These updates will be a result of meeting outcomes surrounding building planning, fundraising, communications and programming initiatives for the new facility.  Project details and economic impact details can always be found here: https://elkhartcenter.com/ and click here to make inquiries about the project.

JULY 2018

Community Commons

  • Detailed structural steel in radius entry
  • Installed decking
  • Continued underground  plumbing
  • Continuing to pour diamonds
  • Continued canopy framing

Fitness and Therapy Center

  • Installed decking on gyms, suspended track
  • Started installation of stairs from track level to concourse level
  • Laid CMU walls in locker rooms and second floor bearing wall
  • Laid CMU walls on track level to underside of deck
  • Continued underground  plumbing
  • Poured second floor slab on deck on partial track and west end around restrooms, while continuing to pour diamonds
  • Continued to rough-in overhead MEP in lockers
  • Poured concrete in whirlpool
  • Installation of exterior metal stud framing
  • Continued spray fireproofing on exterior wall beams of pools, stair tower
  • Started roofing

Aquatics Center

  • Continuing to pour diamonds
  • Continued to rough-in overhead MEP in lockers
  • Continued pool piping
  • Continued spray fireproofing on exterior wall beams of pools, laundry area
  • Completed 95% installation of roofing

General

  • Started installation of siding Z Girts around the building
  • Installed storm drain outlet into Elkhart River