Quarterly, we will be providing project updates on our blog for community members, donors, and partners to learn about how the project is progressing. These updates will be a result of meeting outcomes surrounding building planning, fundraising, communications and programming initiatives for the new facility.  Project details and economic impact details can always be found here: https://elkhartcenter.com/ and click here to make inquiries about the project.

APRIL - MAY 2018

  • Completed steel, began underground plumbing and electrical and began exterior metal stud framing for Beacon fitness and physical therapy units 
  • Completed most of steel detailing in community center
  • Erected and detailed steel in gymnasium and completed masonry on south end of gymnasium
  • Completed masonry on east, west, and north exterior walls and completed underground plumbing and electrical of teaching/fitness and therapy pools. Began pool piping and concrete for whirlpool.
  • Completed masonry on east wall and partial north wall of the main pool
  • Completed installation of underground plumbing and electrical and began spray fireproofing in locker rooms
  • Prepped, formed, and poured recess slab on grade in locker rooms
  • Started overhead rough-in of main pool
  • Started underground pool piping in main pool and storage areas