Quarterly, we will be providing project updates on our blog for community members, donors, and partners to learn about how the project is progressing. These updates will be a result of meeting outcomes surrounding building planning, fundraising, communications and programming initiatives for the new facility.  Project details and economic impact details can always be found here: https://elkhartcenter.com/ and click here to make inquiries about the project.

 
ProjectFloorplan.png

JANUARY - MARCH 2018

  • Erosion control measures in place
  • Continued erection of structural steel at the locker room area upper elevations
  • Completed erection of west stair tower and fitness pool
  • Erected stadia bleacher structural steel
  • Laid CMU wall at track level for precast at concourse
  • Started CMU wall between unit A and C
  • Erected precast planks at concourse level
  • Roughed-in temporary power to unit D locker room area
  • Completed erection of structural steel and epic decking on competition pool
  • Erected precast stadia risers in unit C
  • Laid CMU on east and north exterior walls of teaching/training pools
  • Finished CMU wall between unit A and C to underside of deck
  • Erected precast planks at rook level on unit D
  • Roughed-in underground conduit for unit D for both floors
  • Continued to install underground plumbing, sanitary and storm piping in unit D
  • Received pool equipment and materials, inventories and stored in container
  • Erected unit E structural steel and started detailing
  • Continued masonry on east and north exterior walls of teaching and training pools
  • Started masonry on north and west walls of the main pool
  • Began prepping for slab on grade in unit D