We provide project updates on our blog for community members, donors, and partners to learn about how the project is progressing. These updates will be a result of meeting outcomes surrounding building planning, fundraising, communications and programming initiatives for the new facility.  Project details and economic impact details can always be found here: https://elkhartcenter.com/ and click here to make inquiries about the project.

DECEMBER 2018

BUILDING

  • Continued to rough-in MEP in walls of Units D, E, and H

  • Poured remaining floor slab on Unit F, G, and B mechanical rooms

  • Finished forming, installed rebar, and poured bottom slab for competition pool at 8"‘-1” depth

  • Completed laying brick veneer on north wall of Unit H over doors

  • Continued to lay CMU interior walls

  • Continued to frame interior metal stud walls in Units D, E, F, G, and H

  • Continued installation of Z Girts, flashing, and siding around the building

  • Continued to install window frames and glazing around building

  • Continued spray foam insulation around building

  • Removed asphalt and sidewalk from existing Clark Street and installed subgrade up to design elevation

  • Installed last remaining storm sewer lateral to pond on west side of building