We provide project updates on our blog for community members, donors, and partners to learn about how the project is progressing. These updates will be a result of meeting outcomes surrounding building planning, fundraising, communications and programming initiatives for the new facility.  Project details and economic impact details can always be found here: https://elkhartcenter.com/ and click here to make inquiries about the project.

OCTOBER 2018

Infrastructure

  • Added fill to grade on northeast corner of site for underground power

  • Connected storm and sanitary lines around building

  • Set transformer on pad and installed underground wire from AEP pedestal to transformer

Building

  • Continued to rough-in MEP in walls

  • Finished majority of fitness pool waterproofing and poured steps

  • Poured base of therapy pool and started erecting walls within pool

  • Completed metal stud walls and sheathing for stair towers

  • Framed interior metal stud walls

  • Continued to spray fireproofing

  • Completed rough-in of roofing

  • Completed majority of fire protection piping

  • Continued installation of siding Z Girts and flashing around building

  • Continued spray foam insulation around building

  • Completed painting for pool ceilings

  • Continued brick veneer around units on exterior walls