Monthly, we will be providing project updates on our blog for community members, donors, and partners to learn about how the project is progressing. These updates will be a result of meeting outcomes surrounding building planning, fundraising, communications and programming initiatives for the new facility.  Project details and economic impact details can always be found here: https://elkhartcenter.com/ and click here to make inquiries about the project.

OCTOBER 2017 UPDATE

  • The value engineering efforts continue to find $1MM in project savings.  
  • We will be locking in masonry and those vendors who are in immediate need to keep moving forward.
  • Physical therapy and sports medicine functions will be the medical fitness space focus. Beacon is covering the design costs.  
  • Curbs are in for the parking lot.  Prep for asphalt is underway.
  • Steel is scheduled to start on Wednesday 10/25/17.  Main structural steel will take 2-3 months for topping off.
  • Naming committee for the facility is moving forward with survey.
  • Regional Cities documentation is sent for the first appropriation.
  • Rotary and service organization events are underway at the Lerner Theater.  
  • In the overall fundraising effort, $1.4MM remains to be raised of the $69.5MM.